The process map: one session, six phases, one phase of the release

Each session runs the six phases once, for one phase of the release. The documents carry the state between sessions, not the session itself. The loop closes by writing the next session's starting point.

reads what the phase readswrites what the phase writesAmber bar: a step that is never skipped
  1. 1Sync and orient

    Fetch from the remote before reading any file; bring the local copy level if it is behind.

    Readsprogress log + next pickrelease master spec
    Writesnothing

    Each is read once. A status question is never answered from a tree that has not been fetched.

  2. 2Scope and gate

    Confirm the one phase with the owner, its boundaries and open decisions; then the standing gates.

    Readsthe standing gates, in order
    Writesnothing yet: the scope is agreed, then written in phase 3

    Scope shape by risk: extending existing plumbing is scoped and built in one pass; a new model or an open external question stops at the spec.

  3. 3Spec first

    Write the phase spec before any code: objective, scope in and out, exit checks.

    Readsmaster spec
    Writesphase spec

    Non-functional targets are declared as numbers to be measured. If the scope moves, the spec says so.

  4. 4Build and verify

    Exercise the increment against the running stack with re-runnable scripts; measure each target at a stated scale.

    Readsphase spec
    Writescode-review file + resolutionsbacklog or desktop queue

    Every number tagged measured or projected. The review is written to its own file before the reviewer returns; each finding gets fixed, not taken (with the reason) or deferred.

  5. 5Demo and sign-off

    Run the demo on real data from the runbook; capture the evidence.

    Readsrunbook
    Writesrunbook journeyssign-off log

    Journeys go into the runbook before the demo runs; a serving check confirms the running server is the committed code. No self-sign-off: until the owner approves, it is "built, awaiting sign-off".

  6. 6Close out and hand off

    Commit what changed and why, tag the phase, push, roll off the progress log if over its cap, then end the session.

    Writesuser guideas-built diagrams (at a release)progress log + next pick

    A phase that changed what a user sees updates the user guide in the same session, or the gap is recorded as debt.

The next session starts at phase 1 by reading the progress log and the next pick this one wrote.

At release level

One master spec per release; phase specs drawn from it; increment specs for work that falls between releases. At each release sign-off the living as-built diagrams are updated in place, with git history as their record, and that release's design snapshots are frozen.

Specimen of an HTML visual from the operating model. The method is described in full on The operating model; the delivery loop it sits inside is on The delivery method. Page only; there is no file to download.